The short answer
Measure the full perimeter of the home and the height from the ground to the bottom edge at multiple points.
Let the installer calculate the final amount
Sloped ground, corners, vents, access doors, steps, porches, waste, seams, and the selected system change the material quantity. Use field measurements from the installed home instead of estimating from the floor-plan dimensions alone.
Measure height changes around the perimeter
A rectangular home gives you a starting perimeter, but the ground may not be level all the way around. Measure at the points required by the selected system rather than using one height for the whole house.
Take the measurements to the supplier or installer and include corners, access, vents, and the manufacturer’s cutting and installation requirements. Floor-plan width and length alone do not provide a reliable material order for an uneven site.
Account for openings before ordering
Sketch the perimeter and mark steps, porches, utility access, and changes in ground level. Give that sketch to the supplier with the measurements. Ask which accessories come with the panels and which are separate items. The supplier should work out the final order for its particular system; dividing a total area by a panel size can miss important installation pieces.